High speed data collection programme

Updated: 2 February 2012

Each year, between October and March, we survey the condition of our highways. We do this using a specialist vehicle called ‘SCRIM+’ (Sideway-force Coefficient Routine Investigation Machine). SCRIM+ collects data on range of condition aspects, which allows us to respond to any arising maintenance issues and helps ensure road users continue to travel safely.

Here, you can see the current 2011/12 SCRIM+ survey programme. Simply click on the map area for which you want the details, or check the table below for the survey start and end dates for each area.

Latest Programme for the 2011/12 SCRIM+ survey. Click on appropriate Network Area for details.



Area Name Programmed Survey Start Date Programmed Survey End Date
Wellington 19 December 2011 29 January 2012
East Wanganui 26 January 2012 29 January 2012
Napier 15 November 2011 23 November 2011
Gisborne 19 November 2011 23 November 2011
Bay of Plenty 22 November 2011 25 November 2011
Tauranga / Bay Roads 10 December 2011 11 December 2011
Rotorua 22 November 2011 29 November 2011
East Waikato 29 November 2011 19 December 2011
Auckland 10 January 2012 16 January 2012
PSMC005 10 January 2012 18 January 2012
West Waikato 14 December 2011 19 December 2011
Northland 05 December 2011 09 December 2011
Central Waikato 26 November 2011 29 November 2011
PSMC006 19 January 2012 22 January 2012
West Wanganui 22 January 2012 25 January 2012
West Coast 24 February 2012 7 March 2012
Central Otago 4 February 2012 7 February 2012
Southland 14 February 2012 19 February 2012
Coastal Otago 8 February 2012 13 February 2012
South Canterbury 31 January 2012 3 February 2012
North Canterbury 20 February 2012 23 February 2012
Marlborough 7 March 2012 12 March 2012
Nelson 7 March 2012 12 March 2012