| Review Name | Request Type | Work category | Org Name | Project Name | Phase Type | Profile | Decision | Reason | Total cost change | NLTA share change | Condition |
|---|---|---|---|---|---|---|---|---|---|---|---|
| March Review | New approval | Bridge renewals | Chatham Islands Council | Gillespies Culvert (T funds) | Construction | MMH | Declined | The requirements of section 20 of the Land Transport Management Act 2003 have not been met. Further details regarding the reasons can be accessed on LTP online or by request | 139,402. | ||
| March Review | New approval | Bridge renewals | South Taranaki District Council | Bridge 143 Replacement - Parihaka Road | Construction | MMH | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 340,000. | 204,000. | |
| March Review | New approval | Cycle facilities | BOP Highway & Network Operations | Poike Road Pedestrian & Cycle Facility | Investigation | HMM | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 30,000. | 30,000. | |
| March Review | New approval | Cycle facilities | Christchurch City Council | Railway Cycleway North (Northcote Rd to Tuckers Rd) | Construction | HMH | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 709,050. | 375,797. | |
| March Review | New approval | Cycle facilities | Tasman District Council | Rototai Road Shared Use Path Stage 2 | Construction | HMM | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 79,500. | 46,905. | |
| March Review | New approval | Cycle facilities | Waitakere City Council | Cycleway - Te Atatu Peninsula | Construction | HMH | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 665,000. | 352,450. | |
| March Review | New approval | New roads and structures | Hawkes Bay Highway & Network Operations | HB Expressway Southern Extension | Construction | MMM | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 12,000,000. | 12,000,000. | |
| March Review | New approval | Passenger rail infrastructure | Greater Wellington | Rail Infra - Project Management for Wgtn Area Rail Projects | Construction | MMM | Approved with conditions | Provided the condition(s) have been satisfied, the requirements of section 20 of the Land Transport Management Act 2003 will be met. Further details regarding the decision can be accessed on LTP online or by request | 2,228,000. | 2,005,200. | Subject to apportionment of these costs to particular tasks as stated on page 12 of the Output Agreement for Wellington Metro Rail Upgrade, between the Minister of Finance and ONTRACK. |
| March Review | New approval | Passenger transport road improvements | North Shore City Council | Carlisle Road BPM (East Coast Rd to Browns Bay) | Construction | MMH | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 860,000. | 455,800. | |
| March Review | New approval | Pedestrian facilities | Auckland City Council | Cycling & Walking Implementation (2008/09) | Construction | HMH | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 846,000. | 448,380. | |
| March Review | New approval | Pedestrian facilities | Auckland City Council | Cycling & Walking Implementation (2008/09) - Kepa Rd | Construction | HML | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 230,000. | 121,900. | |
| March Review | New approval | Regional transport studies | Westland District Council | West Coast Regional Walking and Cycling Strategy | Study | HH | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 10,000. | 7,500. | |
| March Review | New approval | Road reconstruction | Gisborne District Council | Lower Tauwhareparae Road (RD) | Construction | HMH | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 900,000. | 900,000. | |
| March Review | New approval | Road reconstruction | Kapiti Coast District Council | Pavement Smoothing | Construction | MMH | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 215,000. | 113,950. | |
| March Review | New approval | Road reconstruction | Palmerston North City Council | Railway Road Improvement. | Construction | MMH | Approved with conditions | Provided the condition(s) have been satisfied, the requirements of section 20 of the Land Transport Management Act 2003 will be met. Further details regarding the decision can be accessed on LTP online or by request | 2,782,000. | 1,557,920. | Funding approval is conditional upon: 1. the intersection with Airport Drive being a roundabout; 2. Council demonstrating commitment to the total project by including the funding for Stage 2 in its LTCCP for 2009/10. |
| March Review | New approval | Road reconstruction | Ruapehu District Council | Dobbs Bluff Reconstruction | Construction | L | Approved in part | The requirements of section 20 of the Land Transport Management Act 2003 (LTMA) have been met for part of the request. The balance of the request is either declined because the requirements of section 20 of the LTMA have not been met or deferred for late | 601,000. | 720,720. | |
| March Review | New approval | Road reconstruction | Ruapehu District Council | Dobbs Bluff Reconstruction | Design | L | Declined | The requirements of section 20 of the Land Transport Management Act 2003 have not been met. Further details regarding the reasons can be accessed on LTP online or by request | 72,000. | ||
| March Review | New approval | Road studies | Auckland City Council | Railway Level Crossings - Feasibility Study | Study | Declined | The requirements of section 20 of the Land Transport Management Act 2003 have not been met. Further details regarding the reasons can be accessed on LTP online or by request | ||||
| March Review | New approval | Road studies | Hastings District Council | Urban Transportation Strategy | Study | HM | Approved with conditions | Provided the condition(s) have been satisfied, the requirements of section 20 of the Land Transport Management Act 2003 will be met. Further details regarding the decision can be accessed on LTP online or by request | 180,000. | 244,800. | Subject to consideration of adjoining linkages/integration with Napier urban area. |
| March Review | New approval | Road studies | Papakura District Council | Takanini Grade separation | Study | Declined | The requirements of section 20 of the Land Transport Management Act 2003 have not been met. Further details regarding the reasons can be accessed on LTP online or by request | ||||
| March Review | New approval | Road studies | Queenstown-Lakes District Council | Walking & Cycling Audits | Study | HH | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 90,000. | 67,500. | |
| March Review | New approval | System use studies | Hamilton City Council | Access Hamilton Study Review | Study | HM | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 406,000. | 304,500. | |
| March Review | New approval | System use studies | North Shore City Council | NSCC Freight Study 08-09 | Study | HH | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 100,000. | 75,000. | |
| March Review | New approval - emergency works | Emergency reinstatement | Hauraki District Council | Effect of Drought in Jan - April 2008 | Construction | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 4,141,000. | 3,492,670. | ||
| March Review | New approval - emergency works | Emergency reinstatement | Waitaki District Council | E/W - Flooding in Waitaki District February 2009 | Construction | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 117,000. | 73,710. | ||
| March Review | Cost / Scope adjustment | Drainage renewals | Central Otago District Council | Maintenance Programme 2008/09 | Local Roads | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 493,000. | 251,430. | ||
| March Review | Cost / Scope adjustment | Emergency reinstatement | Auckland Highway & Network Operations | (E) Waiwhiu Rd Slip Auckland April 07 | Construction | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 2,800. | 2,800. | ||
| March Review | Cost / Scope adjustment | Emergency reinstatement | Franklin District Council | Emergency Works 2008/2009 | Construction | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 303,958. | 155,019. | ||
| March Review | Cost / Scope adjustment | Emergency reinstatement | Gisborne District Council | Emergency Works 08/09 | Construction | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 300,000. | 224,000. | ||
| March Review | Cost / Scope adjustment | Emergency reinstatement | Gisborne Highway & Network Operations | E/Works 08/09 Kemps Hill | Construction | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 371,000. | 371,000. | ||
| March Review | Cost / Scope adjustment | Emergency reinstatement | Hawkes Bay Highway & Network Operations | Emergency Works 07/08 -HB 07/08 Storm. | Construction | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | -200. | -200. | ||
| March Review | Cost / Scope adjustment | Emergency reinstatement | Hurunui District Council | Flood Damage District Wide - July& August 2008 | Construction | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 3,375,180. | 3,168,535. | ||
| March Review | Cost / Scope adjustment | Emergency reinstatement | Hurunui District Council | Flood Damage SPR Road - July 2008 | Construction | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 951,597. | 951,597. | ||
| March Review | Cost / Scope adjustment | Emergency reinstatement | Manawatu/Wanganui Highway & Network Operations | E/W East Wanganui July & August 2008 Storm Events | Construction | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 112,500. | 112,500. | ||
| March Review | Cost / Scope adjustment | Emergency reinstatement | Stratford District Council | E/W Minor Events 07/08 | Construction | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 0. | 2,400. | ||
| March Review | Cost / Scope adjustment | Emergency reinstatement | Stratford District Council | E/W Minor Events 08/09 | Construction | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 123,000. | 68,960. | ||
| March Review | Cost / Scope adjustment | Emergency reinstatement | Waikato Highway & Network Operations | E/W [E] 08/011/3 Raglan Road SH23 | Construction | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 110,000. | 110,000. | ||
| March Review | Cost / Scope adjustment | Emergency reinstatement | Waikato Highway & Network Operations | E/W [E]08/013/3 Tongaporutu Underslip | Construction | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 650,000. | 650,000. | ||
| March Review | Cost / Scope adjustment | Emergency reinstatement | Waikato Highway & Network Operations | E/W CW SH46 Blocked Culvert 15th April 2008 | Construction | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | -200. | -200. | ||
| March Review | Cost / Scope adjustment | Emergency reinstatement | Waitomo District Council | E/W Minor Events 2008/2009 | Construction | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 25,450. | 98,542. | ||
| March Review | Cost / Scope adjustment | Environmental maintenance | Central Otago District Council | Maintenance Programme 2008/09 | Local Roads | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | -35,500. | -18,105. | ||
| March Review | Cost / Scope adjustment | Network and asset management | Central Otago District Council | Maintenance Programme 2008/09 | Local Roads | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | -40,400. | -20,604. | ||
| March Review | Cost / Scope adjustment | Network and asset management | Queenstown-Lakes District Council | Maintenance Programme 2008/09 | Crown Range | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 79,000. | 71,100. | ||
| March Review | Cost / Scope adjustment | Network and asset management | Queenstown-Lakes District Council | Maintenance Programme 2008/09 | Local Roads | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 861,000. | 370,230. | ||
| March Review | Cost / Scope adjustment | Network and asset management | Queenstown-Lakes District Council | Maintenance Programme 2008/09 | SPR | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 92,000. | 92,000. | ||
| March Review | Cost / Scope adjustment | New roads and structures | BOP Highway & Network Operations | Harbour Link | Construction | MMM | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | -22,785,200. | -22,785,200. | |
| March Review | Cost / Scope adjustment | New roads and structures | Tasman Highway & Network Operations | Ruby Bay Bypass A | Construction | LML | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | -2,000,000. | -1,981,926. | |
| March Review | Cost / Scope adjustment | Pavement rehabilitation | Central Otago District Council | Maintenance Programme 2008/09 | Local Roads | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | -252,000. | -128,520. | ||
| March Review | Cost / Scope adjustment | Pavement rehabilitation | North Shore City Council | Maintenance Programme 2008/09 | Local Roads | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 1,071,000. | 460,530. | ||
| March Review | Cost / Scope adjustment | Pavement rehabilitation | Waitaki District Council | Maintenance Programme 2008/09 | Local Roads | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | -203,300. | -115,881. | ||
| March Review | Cost / Scope adjustment | Preventive works | Otago Highway & Network Operations | Nevis Bluff P5 Rock Removal | Construction | MML | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | -382,000. | -382,000. | |
| March Review | Cost / Scope adjustment | Road reconstruction | Auckland City Council | Pavement Reconstruction 2008/09 | Construction | MMH | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 186,000. | 98,580. | |
| March Review | Cost / Scope adjustment | Road reconstruction | North Shore City Council | Pavement Reconstruction 2008/09 | Construction | MMH | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 423,815. | 224,622. | |
| March Review | Cost / Scope adjustment | Road reconstruction | Rodney District Council | Warkworth SH1 Intersection Improvements (Design) | Design | MMH | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 82,500. | 47,850. | |
| March Review | Cost / Scope adjustment | Road reconstruction | Waimakariri District Council | Flaxton Road / Fernside Road Intersection Improvements. | Design | LMM | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 12,000. | 7,080. | |
| March Review | Cost / Scope adjustment | Routine drainage maintenance | Central Otago District Council | Maintenance Programme 2008/09 | Local Roads | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | -53,800. | -27,438. | ||
| March Review | Cost / Scope adjustment | Seal extension | DOC (Mt Cook) | Tasman Valley Road sealing | Design | MMH | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 140,000. | 140,000. | |
| March Review | Cost / Scope adjustment | Sealed pavement maintenance | Central Otago District Council | Maintenance Programme 2008/09 | Local Roads | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 208,200. | 106,182. | ||
| March Review | Cost / Scope adjustment | Sealed road resurfacing | Central Otago District Council | Maintenance Programme 2008/09 | Local Roads | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | -658,000. | -335,580. | ||
| March Review | Cost / Scope adjustment | Sealed road resurfacing | Franklin District Council | Maintenance Programme 2008/09 | Local Roads | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 468,000. | 238,680. | ||
| March Review | Cost / Scope adjustment | Structures component replacements | Central Otago District Council | Maintenance Programme 2008/09 | Local Roads | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 37,960. | 19,359.6 | ||
| March Review | Cost / Scope adjustment | Structures maintenance | Central Otago District Council | Maintenance Programme 2008/09 | Local Roads | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | -57,250. | -29,197.5 | ||
| March Review | Cost / Scope adjustment | Traffic services maintenance | Central Otago District Council | Maintenance Programme 2008/09 | Local Roads | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 91,900. | 46,869. | ||
| March Review | Cost / Scope adjustment | Traffic services renewals | Central Otago District Council | Maintenance Programme 2008/09 | Local Roads | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | -85,707. | -43,710.57 | ||
| March Review | Cost / Scope adjustment | Unsealed pavement maintenance | Central Otago District Council | Maintenance Programme 2008/09 | Local Roads | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 43,300. | 22,083. | ||
| March Review | Cost / Scope adjustment | Unsealed road metalling | Central Otago District Council | Maintenance Programme 2008/09 | Local Roads | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 658,809. | 335,992.59 | ||
| March Review | Cost / Scope adjustment | Unsealed road metalling | Waitaki District Council | Maintenance Programme 2008/09 | Local Roads | Approved | The requirements of section 20 of the Land Transport Management Act 2003 have been met. Further details regarding the reasons can be accessed on LTP online or by request | 80,000. | 45,600. |