Applications to the Environmental Protection Authority (EPA)

Updated: 10 February 2014

The NZ Transport Agency (NZTA) applied for designation and resource consents for the Transmission Gully section of the Wellington Northern Corridor of national significance project (Levin to Wellington Airport) in August 2011.

On this page

View of proposed intersection at SH58 from Silverwood subdivision, Whitby.

View of proposed intersection at SH58 from Silverwood subdivision, Whitby.

About the project

The NZTA applications sought approval to construct 27 kilometres of inland highway through Transmission Gully linking MacKays Crossing in the north with Linden in the south. Transmission Gully is so named because it generally follows the route of the Paekakariki–Takapu Road 110 kV line.

In combination with this application, the Porirua City Council (PCC) sought approval for two roads that will link the new highway with the urban areas of Whitby and Waitangirua. As part of the project, and in order to accommodate the new highway Transpower New Zealand Limited sought consent to reposition the transmission lines between State Highway 58 (SH58) and Mackays Crossing.

All of these applications were lodged under the new national consenting process through the Environmental Protection Authority (EPA).

The EPA was set up as part of a governmental move to streamline and simplify the resource consent application process. One of the benefits of the EPA process is the shorter timeframe for considering applications which, therefore, allows outcomes to be known much more quickly than previously. The entire consenting process, using the EPA path, has taken less than a year.

Project overview map.

Working together

The New Zealand Transport Agency (NZTA), together with the Porirua City Council (PCC) and Transpower New Zealand Limited (Transpower) lodged Notice of Requirement and resource consent applications for the Transmission Gully Proposal comprising:

  • the Main Alignment (proposed new highway) and the Kenepuru Link Road for which applications were made by the NZTA for notices of requirement for new designations and resource consents;
  • Two Link Roads that will connect the Main Alignment with the suburbs of Whitby and Waitangirua for which applications were made by the Porirua City Council for notices of requirement for new designations and resource consents; and
  • The relocation of 24 transmission towers and strengthening of 10 towers required in order to accommodate the Main Alignment for which applications were made by Transpower New Zealand Limited.

The three applicants presented integrated application documents.

Porirua City Council logo. Transpower NZ Limited logo.

How to view the application

You can find all of the Transmission Gully project application and lodgement documents on this site.

To assist you in finding your way around these documents as simply and quickly as possible, we have placed the applications in sections to help you find the information you want faster. A guide to the lodgement documentation (PDF, 2.24MB) has been prepared which explains the nature of all of the documents that are available and how they relate to one another. This document provides a list of all the documents submitted, a list of abbreviations, and a glossary of terms used.

Non-technical summary

This document provides a non-technical summary (PDF, 377KB) of the Resource Management Act (RMA) planning consents assessments for the Transmission Gully project. It summarises the technical reports that were prepared in support of the applications as well as providing more detailed analyses.

Update on consenting process

On 24 August 2011, the Environmental Protection Authority (EPA) recommended to the Minister for the Environment that the regulatory consent applications lodged for the Transmission Gully project be directed to a Board of Inquiry as a proposal of national significance.

On 16 September 2011, the Minister for the Environment directed that the regulatory consent applications lodged for the Transmission Gully project be referred to a Board of Inquiry.

In February-March 2012, the Board of Inquiry heard the applications applied for the Transmission Gully project. On 4 May 2012, the Board of Inquiry released its draft decision on the regulatory consents applications lodged for the Transmission Gully project. The Board's draft decision and information on the comments process can be accessed on the EPA website.

On 22 June 2012, the Board of Inquiry released its final decision on the Transmission Gully applications. The Board’s decision can be accessed on http://www.epa.govt.nz/Resource-management/previous/tg/Pages/Final-report-and-decision.aspx.