Risk assessment procedure

Descriptor Consequence Insignificant Minor Moderate Major Critical
Probability Description Minor delays during clean-up and/or insignificant risk to users Reduced capacity and/or low risk to users Reduced to half the capacity for more than 24 hours and/or unacceptable risk to users Route closed for more than 24 hours and/or major risk to users Sever the route and/or extreme risk to users
Almost Certain Expected to occur in most circumstances High High Extreme Extreme Extreme
Likely Will probably occur in most circumstances Low High High Extreme Extreme
Possible Might occur at sometime Negilible Low High Extreme Extreme
Unlikely Could occur at sometime Negilible Negilible Low High Extreme