The NZTA Procurement manual is to be used for activities funded through the National Land Transport Programme and contains procurement procedures approved by the NZTA for use by approved organisations when purchasing infrastructure, planning and advice, and public transport services. This manual also provides guidance on the application of these procurement procedures and the strategic context within which they operate.

There are a number of tools to assist in the use of the manual.

Read more about the new procurement environment

Procurement manual

Appendix A: Procurement strategy checklist

Print version: Appendix A: Procurement strategy checklist (PDF, 33 KB)

Overview

This appendix contains a checklist to assist approved organisations to develop a procurement strategy. The checklist is a series of headings against which the approved organisation can assess its existing procurement strategy or develop one in accordance with the guidelines in this manual.

Checklist

1. Executive summary

  • 1.1 Summary statements of key issues and opportunities to obtain value for money.
  • 1.2 Recommendations (where relevant) that the NZTA:
    • endorses the procurement strategy
    • approves the use of advanced components
    • approves a customised procurement procedure
    • approves a variation or an exemption to a procurement rule
    • approves the use of in-house professional services.
  • 1.3 Evidence of corporate ownership or internal endorsement of the procurement strategy.

2. Policy context of the approved organisation

  • 2.1 Strategic objectives and outcomes
  • 2.2 Objectives and outcomes for the procurement strategy
  • 2.3 The NZTA's procurement requirements and what they mean for the approved organisation:
    • value for money
    • competitive and efficient markets
    • fair competition among suppliers.
  • 2.4 Other relevant factors, such as organisational policies, wider organisational procurement plans or the regulatory environment.

3. Procurement programme

  • 3.1 Procurement programme, segmented by:
    • size, type or duration
    • complexity, scale, timing, innovation potential, risk, and an assessment of the supplier market
    • need for specialised skills.
  • 3.2 Identification (where relevant) of any pending high-risk or unusual procurement activities.

4. Procurement environment

  • 4.1 Analysis of supplier market
  • 4.2 Analysis of the approved organisation's current procurement spend and profile
  • 4.3 Analysis of the impact of the procurement programmes of other approved organisations and other entities.

5. Approach to delivering the work programme

  • 5.1 Confirmation of specific strategic objectives
  • 5.2 The procurement approach. For each segment of the work programme, the procurement strategy should identify the optimal procurement options as they relate to the strategic objectives. Consider:
    • key attributes and value for money strategy
    • the nature of the activities for each segment of work (eg complexity, scale, timing, innovation potential, risk, and an assessment of the supplier market)
    • aggregation, bundling and the term of term service contracts
    • proposed delivery model(s) and supplier selection method(s)
    • impact of the preferred approach on value for money, fair competition, and competitive and efficient markets
    • risk identification and management
    • approach to contract management.
  • 5.3 Analysis of whether advanced components, customised procurement procedures or variations to procurement rules are required and why.

6. Implementation

  • 6.1 Capability and capacity:
    • description of the current and desired state, including current structure, roles and responsibilities within the wider organisational structure
    • identification of any capability or capacity gaps
    • plan to fill the gaps.
  • 6.2 Internal procurement processes
  • 6.3 Performance measurement and monitoring:
    • NZTA KPIs
    • additional KPIs
    • internal reporting, review and feedback process.
  • 6.4 Communication plan:
    • internal stakeholders
    • other approved organisations and entities
    • supplier market
    • the NZTA.
  • 6.5 Implementation plan
  • 6.6 Corporate ownership and internal endorsement.