Overnight lane closures around Bayfair roundabout for construction of flyover

|

Works at the Bayfair end of the Bay Link project are reaching another milestone with the installation of 12 beams across two spans of the Bayfair flyover during the second weekend of April.

Twelve beams will be installed across two spans of the Bayfair flyover

People can expect overnight lane closures, partial closures of the roundabout and signposted detours in the area while this work is underway. Lane closures and detours will be in place from 7pm each evening until 7am the following morning on Friday 8 and Saturday 9 April to progress construction of the Bayfair flyover. 

Waka Kotahi NZ Transport Agency Regional Manager Infrastructure Delivery, Jo Wilton, says it’s exciting to see progress at the Bayfair end, with Girven Road back to it’s initial configuration and the flyover taking shape. 

“The overnight lane closures will allow the crew to install the main structural element of the new SH2 flyover – 12 concrete beams, locally manufactured in Te Puke, each 28m long and weighing up to 54 tonnes.  

“The beams will be lifted into place with the help of a 300-tonne crane positioned at the Bayfair roundabout,” Ms Wilton says. 

“While this significant piece of work involves extensive planning and staging, we’re expecting only minimal delays as it will all be undertaken at night.  

“All good things come in threes. Following construction of the two bridges spanning the East Coast Main Trunk railway line and SH2 at the Te Maunga interchange, it’s great to see the first beams of the flyover go up.”  

Following placement of the beams, construction will continue on the flyover’s remaining pier and the northern ramp of the flyover will emerge out of the ground. Beams for the third span of the four-span flyover are currently programmed to be installed in late 2022.  

Once the Bayfair flyover is complete, it will improve safety and accessibility and transform how people move through the area. Similar to the Hewletts Road flyover, there will be a lane in each direction, separating heavy vehicles heading to the Port from local traffic. In addition to the flyover lanes, there will be two ground level, grade-separated lanes either side of the flyover for local traffic.

The new flyover will take State Highway 2 traffic over the Bayfair roundabout, separating state highway from local traffic and creating a safer environment. It is expected to open in autumn 2023.

Lane closures and detours 

For the beams to be installed, overnight lane closures, partial closures of the roundabout and signposted detours will be in place in the area, impacting people travelling through the Bayfair roundabout.

Lane closures and detours will differ overnight on Friday 8 and Saturday 9 April to allow the lifting of the beams in two different locations. On both nights, there will be lane closures on all approaches to the Bayfair roundabout to manage traffic flows. 

From 7pm Friday 8 April to 7am Saturday 9 April

People travelling on SH2/Maunganui Road from Mount Maunganui to Papamoa will not be able to proceed straight through the Bayfair roundabout. A detour will be available via Girven Road, Maranui Road and Sandhurst Drive. 

People travelling on Girven Road to Mount Maunganui will not be able to turn right at the Bayfair roundabout. A detour will be available via Marlin Street, Taupo Ave, Farm Street, Concord Ave, Oceanbeach Road and Golf Road.  

People travelling on Girven Road to Papamoa will not be able to turn left at the Bayfair roundabout and a detour will be available via Gloucester Road, Eversham Road and Exeter Street. 

Detours will be signposted and in place – see map for details. 

Download larger map [PDF, 95 KB]

From 7pm Saturday 9 April to 7am Sunday 10 April 

A single lane of SH2 will be available in both directions around the Bayfair roundabout. People travelling from Matapihi to Girven Road and vice versa will not be able to proceed straight through the roundabout.

Detours will be signposted and in place – see map for details.

Download larger map [PDF, 86 KB]

If this work is impacted by weather or other unforeseen issues, it will be carried out on the next available weekend. 

Waka Kotahi thanks motorists, local residents and businesses for their patience.  

For more information, visit: nzta.govt.nz/baylinkdetour

Baypark to Bayfair Link project

Plan ahead for a safe, enjoyable journey. Keep up to date with:

Tags