TRAFFIC UPDATES: Several roads have been impacted by recent weather events. We’ll provide updates on our Journey Planner website as information becomes available. View our traffic map for road closures and delays(external link)

SCAM ALERTS: Report a phishing scam or learn about the latest phishing emails

CONTACT CENTRE WAIT TIMES: Our Contact Centre is currently experiencing significant wait times. View frequently asked questions

ONLINE TRANSACTIONS: We are experiencing issues with credit and debit card transactions on our website. We are working with the payment provider to resolve this as soon as we can. 

CONTACT CENTRE WAIT TIMES: Our Contact Centre is currently experiencing significant wait times. View frequently asked questions

REGO AND RUC LABEL ERROR: There was a postage error with labels purchased on the 15 August 2022. Find out more

ROAD USER CHARGES (RUC) DISCOUNT: Find out more about the temporary RUC reduction scheme

ONLINE SERVICES: We are currently experiencing issues with all our online services at the moment. We are working to resolve the services as soon as possible. We apologise for any inconvenience caused.

COVID-19 SERVICES UPDATE: Information on Waka Kotahi services, extensions and more

ONLINE SERVICES: We currently have an issue with receiving some payments and are working to resolve this issue as quickly as possible. We apologise for any inconvenience.

EASTER WEEKEND – PLAN AHEAD: Heading away for the long weekend? Check our holiday journeys tool(external link)

SCAM ALERTS: Refund email and Vehicle licence (rego) renewal phishing emails

CONTACT CENTRE PHONE LINES: Our Contact Centre phone lines are currently unavailable. View frequently asked questions

Waka Kotahi refutes false claims about Pūhoi to Warkworth motorway

|

Waka Kotahi NZ Transport Agency is refuting claims that the Pūhoi to Warkworth motorway north of Auckland is ready to open to traffic, and says suggestions that Waka Kotahi is ‘holding up’ the road opening are entirely false.

“Waka Kotahi wants to see Pūhoi to Warkworth open as soon as possible. Under the Public Private Partnership (PPP) contract for this project, the timing of the road opening is decided by the Northern Express Group (NX2), the private consortium which is responsible for the finance, design, construction, management and maintenance of the motorway. The road can only open after all of the contractually agreed safety and quality assurance requirements have been met. Building a road that meets these tests is the responsibility of NX2 and its subcontractor, Fletcher/Acciona Joint Venture.

“The road is not open yet for the simple reason that the physical works have not been completed by the contractor, and the required independent quality assurance and safety tests have not been carried out,” says Brett Gliddon, Waka Kotahi Acting Chief Executive.

Only after all construction work has been completed can the contractually and legally required independent quality and safety assurance checks be undertaken to allow the road to be opened for use by the public.

Based on current progress Waka Kotahi anticipates that NX2 and their subcontractor Fletcher/Acciona Joint Venture will be in a position to open the road in the second quarter of 2023.

Waka Kotahi, NX2 and Fletcher/Acciona are fully committed to working together to complete the project to meet the required safety and quality standards as soon as possible and look forward to opening the Pūhoi to Warkworth motorway next year.

Significant progress has also been made on Auckland Transport’s Te Honohono ki Tai – Matakana link road, which will support the significant population growth expected in the area and improve network resilience in Warkworth. The link road will be completed in early 2023, and will open in tandem with the new motorway later in the year.

 