Waka Kotahi NZ Transport Agency says the builder of Transmission Gully CPB HEB is continuing to make good progress fixing construction defects and pavement issues required for the Transmission Gully motorway to open.
Waka Kotahi NZ Transport Agency says recent on-site investigations by Waka Kotahi roading experts shows significant progress has been made by the builder, CPB HEB, towards fixing construction defects and pavement issues required for the Transmission Gully motorway to open.
One additional safety and quality assurance test was met last week by CPB HEB, the builder of Transmission Gully. Some of the outstanding tests require remedial work before they can be met, including the road surface and pavement and construction defects.
An additional two safety and quality assurance tests were met last week by CPB HEB, the builder of Transmission Gully, while work continued onsite on pavement remediation and the stormwater system.