7 Jun 2017
The excavator was walked onto the transporter, when slewing to the rear it over-balanced and one track of the excavator slid off the trailer. Slewing...
19 Dec 2016
During early stages of the project there was an issue around suitable cable rollers to pull the hundreds of kilometers of cables required for the...
14 Dec 2016
The team installing the signage in the tunnel needed to access various locations along the tunnel above the barrier. As standing on the barriers was...
14 Dec 2016
The Shared Path Team had the opportunity to eliminate working at height during the assembly of the super structures for the bridge columns. The assembly...
22 Nov 2016
One of our workers recognised an ergonomic hazard when he was assigned the task of lifting the green plastic grating in the Cross Passages Electrical...
22 Nov 2016
The hydro demolition works on Oakley Creek Bridge used high pressure water at 32K psi to break out sections of the concrete deck. This was...